Control of equipment

The building owner or manager is responsible for ensuring there is an air conditioning inspection report for the central system and the building occupier is responsible for ensuring there is an air conditioning inspection report for the equipment they have installed. In this example each party controls less than 250kW and the first inspection must have happened by 4 January 2011.

The central air conditioning system for the building is 150kW.

Tenant 1 occupies floors 1 and 2 and had additionally installed their own system of 110kW.

The landlord is the relevant person for the control of the central (150kW) system. The tenant is the relevant person for the control of the additional system (110kW) on floors 1 and 2.

Multiple small systems in a building

Where a system consists of a number of small units with an effective rated output of less than 12kW, but the total number of units within the building means that the combined cooling capacity is greater than 12kW then an air conditioning inspection is required.

The example below shows an air conditioning system with a cooling capacity greater than 250kW that serves multiple separate rooms. Although the air conditioning system serves multiple separate rooms, some with cooling capacity as low as 3kW per room, the air conditioning system is a single system under single control for the whole building with a cooling capacity greater than 250kW. An air conditioning inspection on a system with a cooling capacity greater than 250kW should have been carried out by 4 January 2009. A revised air conditioning inspection report would be required every 5 years from the date of the initial inspection.

Hotel has 50 rooms. Each room has a cooling capacity of 3 kW. The System is under the control of the hotel chain. The total under single control is 270kW, 150kW in rooms and 120kW for the reception rooms and restaurants. The first inspection must have taken place by 4 January 2009.

Equipment under single control in parts of a building

The example below shows an air conditioning system with a cooling capacity greater than 250kW that serves three separate parts of a building that are designed for separate use. Although the air conditioning system serves three parts of a building that are designed for separate use the air conditioning system is a single system under single control for the whole building with a cooling capacity greater than 250kW. An air conditioning inspection on a system with a cooling greater than 250kW should have been carried out by 4 January 2009. A revised air conditioning inspection report would be required every 5 years from the date of the initial inspection.

Units 1, 2 and 3 are parts within a building. They are designed or altered to be used separately.

The air conditioning system serves units 1, 2 and 3 and are controlled by the same person.

Together the total capacity controlled is > 250kW.

The first inspection must have been completed by 4 January 2009.

Equipment under single control in separate buildings

Where an individual building benefits from the refrigeration plant of an air conditioning system under single control, the building owner or manager is responsible for obtaining an air conditioning inspection report if the rating of the local cooling plant in the building is greater than 12kW.

The buildings are not covered by the air conditioning plant under single control, unless the systems in these buildings are a permanent part of the air conditioning system.

The example below shows an air conditioning system with a cooling capacity greater than 250kW that serves four separate buildings. Although the air conditioning system serves four separate buildings the air conditioning system is a single system under single control with a cooling capacity greater than 250kW. An air conditioning inspection on a system with a cooling capacity greater than 250kW should have been carried out by 4 January 2009. A revised air conditioning inspection report would be required every 5 years from the date of the initial inspection.

Air conditioning systems in buildings 1-4 are part of a district cooling system and are controlled by the same person.

Together the total capacity controlled is > 250kW.

The first inspection must have been completed by 4 January 2009.

Cooling capacity, where occupants benefit from additional cooling capacity

In this example, a building is served by a single system of more than 250kW capacity under single control with an additional air conditioning system rated at 100kW.

An air conditioning inspection on a system with a cooling capacity greater than 250kW should have been carried out by 4 January 2009. A revised air conditioning inspection report would be required every 5 years from the date of the initial inspection.

The building is served by a single system under single control < 250kW. In addition an air conditioning system of 100kW has been installed to serve the trading floor. The total under single control is >250kW. The first inspection must have been completed by 4 January 2009.

The occupants on the trading floor are using machines rather than solely running the process. Any additional air conditioning capacity, therefore, benefits the occupants and is included in the air conditioning capacity to be inspected.